Message type: E = Error
Message class: 61 - Fehlermeldungen fuer Bedarfsplanung
Message number: 056
Message text: Planned order only partially converted
You have only entered a partial amount of the planned order quantity
for conversion.
The planned order will, therefore, only be partially converted. The
planned order quantity is only reduced by the quantity that was
converted.
You can convert the rest of the planned order quantity at a later date.
Error message extract from SAP system. Copyright SAP SE.
61056
- Planned order only partially converted ?The SAP error message "61056 Planned order only partially converted" typically occurs during the conversion of planned orders to production orders in the SAP system. This message indicates that not all components or operations associated with the planned order could be successfully converted into a production order. Here are some common causes, solutions, and related information for this error:
Causes:
- Insufficient Stock: There may not be enough stock of the required components to fulfill the planned order.
- Capacity Constraints: The work center may not have enough capacity available to accommodate the planned order.
- Missing Master Data: Required master data (like BOM, routing, or work center) may be incomplete or incorrect.
- Scheduling Issues: The planned order may be scheduled in a way that conflicts with other orders or maintenance activities.
- Status of Planned Order: The planned order may be in a status that does not allow full conversion (e.g., partially released).
- Batch Management: If batch management is enabled, there may be issues with batch determination.
Solutions:
- Check Stock Levels: Verify that there is sufficient stock of all components required for the planned order. If not, procure the necessary materials.
- Review Capacity: Check the capacity of the work center and ensure that it can handle the planned order. You may need to adjust the scheduling or reschedule other orders.
- Validate Master Data: Ensure that all relevant master data (BOM, routing, work center) is correctly set up and complete.
- Adjust Scheduling: Review the scheduling of the planned order and make adjustments if there are conflicts with other orders or maintenance.
- Change Status: If the planned order is not in a suitable status for conversion, change its status to allow for full conversion.
- Batch Management: If applicable, ensure that batch determination is correctly set up and that the required batches are available.
Related Information:
MD04
(Stock/Requirements List) to check stock levels and CO01
(Create Production Order) to manually create production orders.By addressing the underlying causes and following the suggested solutions, you should be able to resolve the "61056 Planned order only partially converted" error in SAP.
Get instant SAP help. Start your 7-day free trial now.
61055
Error in the number assignment (Number range: Module &: &)
What causes this issue? This error should not occur.System Response The system issues an error message and will not allow you to continue with this ...
61054
MRP carried out for & & &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
61057
Planned order deleted
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
61058
Error reading forecast parameters for material & in plant & &
What causes this issue? You wanted to plan a material which requires forecast parameters. However, the forecast parameters have not yet been defined ...
Click on this link to search all SAP messages.