Message text: Material &1 &2 &3 is not planned automatically
The material &V1& in plant &V2& or in MRP area &V3& is not included in
automatic MRP because
either the MRP data for plant &V2& or MRP area &V3& has not been
created
or an MRP type has been entered for the material in plant &V2& or MRP
area &V3& that does not allow automatic MRP
INCLUDE NA_SACHVERHALT
Error message extract from SAP system. Copyright SAP SE.
61008
- Material &1 &2 &3 is not planned automatically ?The SAP error message 61008, which states "Material &1 &2 &3 is not planned automatically," typically occurs in the context of materials planning within the SAP system, particularly in the Material Requirements Planning (MRP) process. This error indicates that the specified material is not set up to be planned automatically, which can be due to several reasons.
Causes:
- MRP Type: The material may not have an appropriate MRP type assigned. For example, if the MRP type is set to "ND" (No MRP), the system will not plan the material automatically.
- Planning Parameters: The planning parameters for the material may not be configured correctly. This includes settings like lot size, safety stock, and reorder point.
- Material Status: The material may have a status that prevents it from being planned, such as being marked as "blocked" or "inactive."
- Plant Settings: The plant settings for the material may not allow for automatic planning. This can include settings in the material master or plant-specific parameters.
- Forecasting: If the material is dependent on forecasting and the forecast is not set up, it may not be planned automatically.
Solutions:
- Check MRP Type: Go to the material master (transaction MM03) and check the MRP type assigned to the material. If it is set to "ND," change it to an appropriate MRP type (e.g., "PD" for MRP).
- Review Planning Parameters: Ensure that the planning parameters such as lot size, safety stock, and reorder point are correctly configured in the material master.
- Material Status: Check the material status in the material master. If it is blocked or inactive, change the status to allow planning.
- Plant Settings: Verify the plant-specific settings for the material. Ensure that the plant is set up for MRP and that the material is included in the planning run.
- Forecasting Setup: If the material relies on forecasting, ensure that the forecast is set up correctly and that the material is included in the forecast.
Related Information:
By addressing the above points, you should be able to resolve the error message 61008 and ensure that the material is planned automatically in the SAP system.
Get instant SAP help. Start your 7-day free trial now.
61007
The processing of customer data is not allowed here
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
61006
Please enter completion date and/or start date
What causes this issue? Either a planned finish or a planned start date must be entered for scheduling the planned order.System Response If you ente...
61009
Please specify the order deadlines in ascending order
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
61010
Planned order & will be created
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...