Do you have any question about this error?
Message type: E = Error
Message class: FARR_INFLIGHT_CHECK -
Message number: 052
Message text: C26: Inkorrekter prosp. AbspBetrag an AbgrenzPos. für LV &1 in Vertrag &2
Contract change can either be:
Contract modification
Change of estimates.
Depending on the Customizing (
<DS:SIMG.FARR_VC_ACCT_PR>Configure Accounting Principle-specific
Settings</>) for a company code and accounting principle, one or the
other is applied when the scope of a contract is changed.
The change mode for a POB is determined by the field CHANGE_MODE (only
in the buffer, not written to database) and can be one of the following:
'P' or 'V' prospective change
'R' retrospective change
' ' (empty) no change
Prospective change
In case of a prospective change the system performs a prospective split
on the deferral items. The deferral item which corresponds to an open
reconciliation key in the period of the contract change is flaged with
the prospective split flag (PRO_SPLIT = 'X').
The split amount, that represents the revenue amount posted in periods
prior to the current change, is stored on all deferral items beginning
from the period in which the contract change was performed.
The example below illustrates this:
RECON_KEY,,POB_ID,,CONDITION_TYPE,,REV_QTY_DELTA,,REV_QTY_POSTED,,
PRO_QTY_CUMULATE,,HAS_PRO_SPLIT,,LATEST_DEFITEM
201802001,,POB1,,PR00,,1000.00,,0.00,,0.00,,-,,-
201803001,,POB1,,PR00,,1000.00,,1000.00,,0.00,,-,,-
201803002,,POB1,,PR00,,- 500.00,,1000.00,,1000.00,,X,,-
201804001,,POB1,,PR00,,1000.00,, 500.00,,1000.00,,-,,-
201805001,,POB1,,PR00,,1000.00,,1500.00,,1000.00,,-,,X
In this example, a contract modification was performed in period
2018/03. Therefore the split amount is calculated and the prospective
split flag set. All deferral items, beginning from the contract change
period, are updated with the split amount (PRO_AMT_CUMULATE).
If the split amount on the last deferral item in the contract change
period (here 2018/03) deviates from the split amount on the latest
deferral item, a C26 inflight check error is raised.
Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.
The RAI processing is stopped or the manual transaction from the UI is
stopped.
You can search for SAP notes related to inflight check C26 by using the
terms FARR_INFLIGHT_CHECK and C26.
You can also check if there is inconsistent data already in the system.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
FARR_INFLIGHT_CHECK052
- C26: Inkorrekter prosp. AbspBetrag an AbgrenzPos. für LV &1 in Vertrag &2 ?Get instant SAP help. Start your 7-day free trial now.
FARR_INFLIGHT_CHECK051
C26: Betrag f. prosp. Abspaltung ist inkonsistent für LV &1 in Vertrag &2
Was verursacht dieses Problem? Contract change can either be: ?Contract modification ?Change of estimates. Das System gibt eine Fehlermeldung aus u...
FARR_INFLIGHT_CHECK050
C02: TRX Preis (AbgrPos.) &4 <> gepl. Erlös &3 für Kondition &2 für LV &1
Was verursacht dieses Problem? The sum of DOC_AMT_CUMULATE and PRO_AMT_CUMULATE for latest deferral items for a condition type is not equal to the ...
FARR_INFLIGHT_CHECK053
C26: Menge v. pro. Abspalt. inkonsistent mit erf. Menge f. LV &1 Vert. &2
Was verursacht dieses Problem? Contract change can either be: Contract modification Change of estimates. Depending on the Customizing ( <DS:SIMG...
FARR_INFLIGHT_CHECK054
C27: Geplanter Erlös &1 <> gebuchter Erlös &2 für Kond. &3 für LV &4
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.