How To Fix DPR_SHARED216 - &1 &2: Fester/Iststart kollidiert mit Termin eines Nachfolgers


SAP Error Message - Details

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 216

  • Message text: &1 &2: Fester/Iststart kollidiert mit Termin eines Nachfolgers

  • Show details Hide details
  • Was verursacht dieses Problem?

    During backward scheduling of the project element, the system calculated
    a start from a successor relationship and the duration of the project
    element. The start is before the fixed start or before the actual start
    of the project element.

    Systemantwort

    The system ignores the successor relationship and uses the fixed start
    or the actual start as the calculated start of the project element.
    The system calculates the finish from this date using the duration of
    the project element.

    Wie behebe ich diesen Fehler?

    Check whether the fixed start or actual start is realistic.

    Vorgehensweise für Systemadministratoren

    Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.


    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


Smart SAP Assistant

  • Was ist die Ursache und Lösung für den SAP Fehler DPR_SHARED216 - &1 &2: Fester/Iststart kollidiert mit Termin eines Nachfolgers ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.