Do you have any question about this error?
Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 215
Message text: &1 &2: Berechnete Termine liegen außerhalb des vorgegebenen Terminrahmens
The calculated dates of the project element are outside the time frame
defined by the superior project element.
Example:
You have set the <ZK>Finish no earlier than</> constraint on a phase.
The scheduling type of the corresponding project is <ZH>bottom-up
scheduling</>.
Due to a change to the duration of a subtask, the duration of the phase
is adjusted (bottom-up scheduling) which violates the constraint.
The scheduling type of the corresponding project is <ZH>top-down
scheduling</>.
The first subtask that violates the time frame that was defined by the
phase is shown.
The calculated dates of the project element are accepted despite the
fact that they exceed the time frame.
Check for the affected project element whether the duration,
constraints, and links to other project elements are realistic.
Check for the superior project element whether the duration and
constraints are realistic.
Example (above):
<ZH>Bottom-up scheduling</>
Either adjust the duration of the subtasks or move the constraint from
the phase to the subtasks so that the duration of the phase is
influenced accordingly.
<ZH>Top-down scheduling</>
Either adjust the duration of the subtasks or the constraint on the
phase.
Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
DPR_SHARED215
- &1 &2: Berechnete Termine liegen außerhalb des vorgegebenen Terminrahmens ?Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED214
&1 &2: Endeinschränkung kollidiert mit Start des Terminrahmens
Was verursacht dieses Problem? The system calculated a start date using the fixed finish date and the duration of the project element. This fixed s...
DPR_SHARED213
&1 &2: Starteinschränkung kollidiert mit Ende des Terminrahmens
Was verursacht dieses Problem? The system calculated a finish date using the fixed start date and the duration of the project element. This finish ...
DPR_SHARED216
&1 &2: Fester/Iststart kollidiert mit Termin eines Nachfolgers
Was verursacht dieses Problem? During backward scheduling of the project element, the system calculated a start from a successor relationship and t...
DPR_SHARED217
&1 &2: Fester oder Iststart kollidiert mit Ende des Terminrahmens
Was verursacht dieses Problem? The system calculated a finish from the fixed start or the actual start and the duration of the project element. The...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.