How To Fix DPR_SHARED207 - Verknüpfungen bilden Zyklus - Terminierung nicht möglich


SAP Error Message - Details

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 207

  • Message text: Verknüpfungen bilden Zyklus - Terminierung nicht möglich

  • Show details Hide details
  • Was verursacht dieses Problem?

    The links form a <ZH>loop</>; scheduling is not possible.

    Systemantwort

    The links between the project elements form a <ZH>loop</>.

    Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.

    The system sees both <ZH>relationships</> between the project elements
    and <ZH>structural relationships</> (single-level) between the project
    elements as <ZH>links</>.
    Example:
    <ZK>Ph1</>
    <ZK> T11</>
    <ZK> T111</>
    <ZK> T12</>
    A relationship has been defined between the task <ZK>T11</> and the task
    <ZK>T12</>. The system creates the following links from this
    relationship (<ZK>T11, T12</>) [(predecessor, successor)]. The system
    then uses the structure relationship to create additional links
    dependent on the scheduling type for the tasks <ZK>T11</> and <ZK>T12</>
    below the phase <ZK>Ph1</> and for the task <ZK>T111</> below the task
    <ZK>T11</>:
    Bottom-up: (<ZK>T11, Ph1</>), (<ZK>T12, Ph1</>), (<ZK>T111, T11</>)
    Top-down: (<ZK>Ph1, T11</>), (<ZK>Ph1, T12</>), (<ZK>T11, T111</>)
    1. Setting up a sort order for processing
    The system tries to sort the project elements within scheduling for
    processing, based on the links. There are now two cases in which the
    message can appear:
    a) During sorting, the system finds at least one project element for
    which a loop via the links (predecessor, successor, relationship) is
    possible.
    b) This kind of sorting cannot be set up. At least one project element
    that does not have a predecessor via the links is required for this.
    2. Creating a relationship
    The message can also appear when you create a relationship. This is the
    case if the system is to create a relationship for two project elements
    P1 and P2 with P1 as the predecessor and P2 as the successor, and a
    higher-level project element PP1 of P1 exists and a higher-level project
    element PP2 of P2 exists and these are linked by a relationship with PP1
    as the successor and PP2 as the predecessor.
    Example:
    <ZK>Ph1</>
    <ZK> T11</>
    <ZK> T111</>
    <ZK> T12</>
    <ZK>Ph2</>
    <ZK> T21</>
    <ZK> T22</>
    A relationship always exists between the phase <ZK>Ph1</> and the phase
    <ZK>Ph2</> in the system with <ZK>Ph1</> as the predecessor and <ZK>Ph2
    </> as the successor. The system then tries to create a relationship
    between the task <ZK>T21</> as predecessor and the task <ZK>T12</> as
    the successor.

    Systemantwort

    The project elements cannot be sorted, therefore, scheduling cannot be
    carried out and the relationship cannot be created. The system resets
    the data.

    Wie behebe ich diesen Fehler?

    Remove the loop by deleting the relationships between the project
    elements as appropriate.

    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


Smart SAP Assistant

  • Was ist die Ursache und Lösung für den SAP Fehler DPR_SHARED207 - Verknüpfungen bilden Zyklus - Terminierung nicht möglich ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker