Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 724
Message text: Auftrag & Vorgang & beginnt in der Vergangenheit
The system is to dispatch an operation.
The indicator <ZH>Indicator forwards</> is not set in the
strategy profile in Customizing for Capacity Planning. That means that
the systems looks for a possible dispatch date in the <ZH>past</>.
The latest start that has been located lies in the past.
Either dispatch the operation manually or
select a strategy profile with the planning direction <ZH>forwards</>,
and dispatch the operation again.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CY724
- Auftrag & Vorgang & beginnt in der Vergangenheit ?Get instant SAP help. Start your 7-day free trial now.
CY723
Auftrag & Vorgang & liegt außerhalb des Puffers Sicherheitszeit
Was verursacht dieses Problem? An operation is to be dispatched so that it lies outside the float after production. However, in the strategy profil...
CY722
Auftrag & Vorgang & außerhalb des Puffers Vorgriffszeit + Vorgangspuffer
Was verursacht dieses Problem? An operation is to be dispatched so that it lies outside the float before production and the operation float. Howeve...
CY725
& gehört nicht zum Ressourcennetz & im Werk &
Was verursacht dieses Problem? The header data of the process order specifies that the operations on resource network structure &V2& are to...
CY726
& hat keine Verbindung zum Vorgänger & im Ressourcennetz & in Werk &
Was verursacht dieses Problem? The header data of the process order specifies that the operations must be scheduled on a particular resource networ...