Do you have any question about this error?
Message type: E = Error
Message class: CP - Task list messages: Core data
Message number: 434
Message text: Achtung: Der Standardlinienplan wird bereits verwendet
You are attempting to change a reference rate routing which is already
referenced in other task lists. The changes you make to this reference
rate routing have direct effects on the referenced task lists.
You can use a where-used list to find out the task lists in which the
reference rate routing is used.
To do this, from the routings main menu, select the menu options
<LS>Reporting -> Where-used -> Ref. operation sets</>.
<DS:TRAN.CA90>Execute where-used list</>
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CP434
- Achtung: Der Standardlinienplan wird bereits verwendet ?Get instant SAP help. Start your 7-day free trial now.
CP433
Achtung: Der Standardplan wird bereits verwendet
Was verursacht dieses Problem? You are attempting to change a reference operation set that is referenced in other task lists. These task lists will...
CP431
Standardplan & zum Löschen vorgemerkt
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CP435
Standardarbeitsplan & & ist nicht vorhanden
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CP436
Vorgang wurde referiert; die Änderung der Daten ist nicht möglich
Was verursacht dieses Problem? The operation for which you want to calculate standard values is referenced from a reference operation set. You can...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.