Black Friday is ending this Friday! 40% off with coupon CYBER40 - Sign up here →
Message type: E = Error
Message class: CP - Task list messages: Core data
Message number: 433
Message text: Achtung: Der Standardplan wird bereits verwendet
You are attempting to change a reference operation set that is
referenced in other task lists. These task lists will also be changed
if you make changes to this reference operation set.
Check what effect changes to the reference operation set will have on
the referenced task lists. Use the where-used report for task lists.
In routings, select the menu options <LS>Reporting -> Where-used ->
Ref. operation sets</>.
<DS:TRAN.CA90>Execute where-used list</>
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
Get instant SAP help. Sign up for our Free Essentials Plan.
CP431 Standardplan & zum Löschen vorgemerkt
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
CP430 Standardplan konnte mit Vorgangsintervall & nicht aufgelöst werden
Was verursacht dieses Problem? The operations of the referenced operation set cannot be inserted with the specified operation increment because the...
CP434 Achtung: Der Standardlinienplan wird bereits verwendet
Was verursacht dieses Problem? You are attempting to change a reference rate routing which is already referenced in other task lists. The changes y...
CP435 Standardarbeitsplan & & ist nicht vorhanden
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.