How to use CO48 - Conv.plan.ord.to prod.ord.part.redct


SAP Transaction Code - Details

  • Transaction Code: CO48

    Description: Conv.plan.ord.to prod.ord.part.redct

    Release: S/4HANA and ECC 6

    Menu Path:

    • Logistics > Production > MRP > Planned Order > Convert to Production Order > Partial Conversion
    • Logistics > Production - Process > MRP > Planned Order > Convert to Production Order > Partial Conversion
  • Show technical details Hide technical details
    • Program:

      Screen: 0

      Authorization Object:

    • Development Package: CO

      Package Description: Application Development ERP PP Production Orders

      Parent Package: APPL

    • Module/Component: PP-SFC

      Description: Production Orders


Smart SAP Assistant

  • SAP Tcode: CO48 - Conv.plan.ord.to prod.ord.part.redct
    .
    
    Overview: 
    CO48 is an SAP transaction code used to convert planned orders into production orders with partial reductions. It is part of the Production Planning (PP) module and is used to reduce the quantity of a planned order without having to delete it. 
    
    Functionality: 
    CO48 allows users to reduce the quantity of a planned order without having to delete it. This can be useful when the quantity of a planned order needs to be reduced but the order itself still needs to be kept in the system. The transaction code also allows users to convert the planned order into a production order with the reduced quantity. 
    
    Step-by-step How to Use: 
    1. Enter transaction code CO48 in the command field. 
    2. Select the planned order that needs to be reduced and click “Reduce”. 
    3. Enter the new, reduced quantity in the “Reduction Quantity” field and click “Save”. 
    4. The planned order will now be reduced to the new quantity and can be converted into a production order if needed. 
    5. To convert the planned order into a production order, select it and click “Convert”. 
    6. Enter any additional information needed for the production order and click “Save”. 
    7. The planned order will now be converted into a production order with the reduced quantity. 
    
    Other Recommendations: 
    It is important to note that CO48 only works with planned orders and not with production orders or other types of orders. Additionally, it is recommended that users check all relevant information before converting a planned order into a production order, as this cannot be undone once completed.
    • Do you have any question about this t-code?


      Upgrade now to chat with this t-code.

Related SAP Transaction Codes

Click the links below to see the following related SAP tcodes:
  • CO47 - Change comparison...

  • CO46 - Order progress report...

  • CO51 - Send Process Messages...

  • CO52 - Evaluate Process Data...


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker