How to use CJ08 - Display Project Definition


SAP Transaction Code - Details

  • Transaction Code: CJ08

    Description: Display Project Definition

    Release: S/4HANA and ECC 6

    Menu Path:

    • Logistics > Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Project Definition > Display
    • Accounting > Investment Management > Investment Projects > Master Data > Work Breakdown Structure (WBS) > Project Definition > Display
    • Accounting > Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Project Definition > Display
  • Show technical details Hide technical details
    • Program: SAPLCJWB

      Screen: 100

      Authorization Object: C_PROJ_TCD

    • Development Package: CN_PSP_OPR

      Package Description: Operative Work Breakdown Structure

      Parent Package: APPL

    • Module/Component: PS-ST-OPR

      Description: Operative Structures


Smart SAP Assistant

  • SAP Tcode: CJ08 - Display Project Definition
    
    Overview: 
    The SAP transaction code CJ08 is used to display the project definition in the system. It is used to view the project definition and its associated data. 
    
    Functionality: 
    The CJ08 transaction code allows users to view the project definition and its associated data. This includes the project type, description, start and end dates, and other related information. It also allows users to view the project's budget, cost elements, and other related information. 
    
    Step-by-step How to Use: 
    1. Enter the transaction code CJ08 in the command field. 
    2. Enter the project number in the Project field. 
    3. Click on Execute (F8). 
    4. The project definition and its associated data will be displayed on the screen. 
    5. To view the budget, cost elements, and other related information, click on the Budget/Cost Elements tab. 
    6. To view the project's documents, click on the Documents tab. 
    7. To view the project's activities, click on the Activities tab. 
    8. To view the project's milestones, click on the Milestones tab. 
    9. To view any changes made to the project definition, click on the Changes tab. 
    10. To save any changes made to the project definition, click on Save (Ctrl+S). 
    11. To exit from this transaction code, click on Back (F3). 
    
    Other Recommendations: 
    It is recommended that users familiarize themselves with all of the tabs available in this transaction code before making any changes to a project definition or its associated data. Additionally, it is important to save any changes made before exiting from this transaction code in order to ensure that all changes are properly recorded in the system.
    • Do you have any question about this t-code?


      Upgrade now to chat with this t-code.

Related SAP Transaction Codes

Click the links below to see the following related SAP tcodes:
  • CJ07 - Change Project Definition...

  • CJ06 - Create Project Definition...

  • CJ11 - Create WBS Element...

  • CJ12 - Change WBS Element...


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker