How to use CM37 - Kapazitätsabgl.: PI Auftrag tab.


CM37 - Overview

  • Transaction Code: CM37

    Description: Kapazitätsabgl.: PI Auftrag tab.

    Release: S/4HANA and ECC 6

    Menu Path:

    • Logistics > Production - Process > Process Planning > Capacity leveling > Process order view > Capacity planning table (table)
    • Logistics > Production - Process > Process Management > Environment > Process Planning > Capacity leveling > Process order view > Capacity planning table (table)
  • Show technical details Hide technical details
    • Program:

      Screen: 0

      Authorization Object:

    • Development Package: CY01

      Package Description: Application Development ERP Resource Planning

      Parent Package: APPL

    • Module/Component: PP-CRP-LVL

      Description: Capacity Leveling


CM37 - Details

  • SAP Tcode: CM37 - Kapazitätsabgl.: PI Auftrag tab.
    
    Overview:
    CM37 is a SAP transaction code used to level the capacity of production orders in the Production Planning (PP) module. It is used to ensure that the capacity of production orders is evenly distributed over a given period of time. This helps to avoid bottlenecks and delays in production. 
    
    Functionality: 
    CM37 allows users to level the capacity of production orders by setting a target date for each order. The system then calculates the optimal start and end dates for each order, based on the available capacity and the target date. This helps to ensure that all orders are completed on time and that there are no delays in production. 
    
    Step-by-step How to Use: 
    1. Enter CM37 in the SAP command field. 
    2. Select the PI order tab. 
    3. Select the production orders you want to level. 
    4. Enter a target date for each order. 
    5. Click “Level” to calculate the optimal start and end dates for each order. 
    6. Click “Save” to save your changes. 
    
    Other Recommendations: 
    It is recommended that users check the capacity of each order before leveling it, as this will help to ensure that all orders are completed on time and that there are no delays in production. Additionally, users should also check the availability of resources before leveling an order, as this will help to ensure that all orders are

    Already have an account? Login here!

CM37 - Related Tcodes

  • CM36 - Kapazitätsabgl.: PI Auftrag graf....

  • CM35 - Kapazitätsabgl.: PI Arbeitspl. tab....

  • CM38 - Kapaz. Planung Langfristplanung...

  • CM40 - KAPA-Abgleich im Batch...


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant