PJ
›
PJ660
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 660
Message text: Sous-activité & définie deux fois (à vérifier)
The MPX files has the same name several time for the same field
<ZH>Activity notes</>. The project system creates the number for the
activity element from the activity notes during the upload.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Check the names you have used for activity notes in Microsoft Project
(R) and make any changes necessary.
Please note:
The numbers for the activity elements in a standard network may not be
identical to each other or to the activity numbers (Field <ZH>activity
notes</>).
Extrait du message d'erreur du système SAP. Copyright SAP SE.
PJ660
- Sous-activité & définie deux fois (à vérifier) ?Get instant SAP help. Start your 7-day free trial now.
PJ650
Activité & définie deux fois (à vérifier)
Quelle est la cause de ce problème? The MPX files have the same name several times for the same field <ZH>Text10</>. The project system...
PJ640
Activité &: ressource affectée & n'est pas définie (à vérifier)
Quelle est la cause de ce problème? You have defined resources for an activity that do not exist in Microsoft Project (R).Réponse du système INC...
PJ670
Poste de travail & défini deux fois (à vérifier)
Quelle est la cause de ce problème? The MPX files has the same name several time for the same field <ZH>Short text</>. The project syst...
PJ680
Liaison & définie deux fois (à vérifier)
Quelle est la cause de ce problème? You have entered a relationship with the same type for the same activity several times in field <ZH>prede...