Do you have any question about this error?
Message type: E = Error
Message class: ORB - Project-Related Incoming Orders/Open Orders
Message number: 109
Message text: La hiérarchie complète est requise pour le traitement
In the settings for results analysis key &V1&, you have stipulated that
the incoming order categories "New order" and "Cancellation" are
determined for the whole project.
However, the data selection matching the specified selection criteria
does not cover all the objects for the project.
Processing stopped.
Change the selection criteria so that all the objects for the project
are selected from the database.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
ORB109
- La hiérarchie complète est requise pour le traitement ?Get instant SAP help. Start your 7-day free trial now.
ORB108
Valeurs d'entrée d'ordres imputées au cours de périodes suivantes
Quelle est la cause de ce problème? You have already settled the incoming order values for the current object to a subsequent period. A new calcula...
ORB107
Le niveau hiérarchique de la structure de facture n'est pas cohérente
Quelle est la cause de ce problème? The determination of the characteristices "New order" and "Order cancellation" for the hist...
ORB200
Il existe des valeurs d'entrée de commandes pour cet objet
Quelle est la cause de ce problème? Incoming order values have already been determined for this object. To avoid data inconsistencies, you cannot c...
ORB201
Annulez d'abord l'imputation
Quelle est la cause de ce problème? For this object, <DS:GLOS.3526C58AAFAB52B9E10000009B38F974>p roject-related incoming order values have al...
Cliquez sur ce lien pour rechercher tous les messages SAP.