Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 109
Message text: Aucun prix n'a pu être déterminé pour la ressource &1 sur ctre cts &2
You want to carry out resource planning for resource &V1& on cost
center &V2&.
In fiscal year &V3&, version &V4&, the system could not determine a
valid price for this combination using the default conditions and
access sequences.
In planning, the system takes a resource price equal to zero for
valuation.
Maintain valid prices for resource &V1&, for cost center &V2&, in
fiscal year &V3&, version &V4&, or change the access sequence in the
conditions.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
Get instant SAP help. Sign up for our Free Essentials Plan.
K8108
La nat. compt. & est bloquée ou est pourvue du code de suppression.
Quelle est la cause de ce problème? You want to include cost element &V1& in a resource master record. You cannot use this cost element, as...
K8107
La ressource &1 peut uniq. être pré-budgétée sous la nat. compt. &2
Quelle est la cause de ce problème? You want to plan resource &V1& under cost element &V4&. However, in the master record for this ...
K8110
Le prix de la ressource & n'est pas connu dans toutes les périodes
Quelle est la cause de ce problème? You want to carry out resource planning for resource &V1& on cost center &V2&. In fiscal year &...
K8111
La nat. compt. secondaire & n'est pas autorisée pour la p-budg. de ress.
Quelle est la cause de ce problème? You want to carry out a resource planning with cost element &V1&. However, in fiscal year &V2&...
Cliquez sur ce lien pour rechercher tous les messages SAP.