Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 749
Message text: Ordre &, opération & : date de fin limite dépassée
Once the operation has been dispatched the finish date constraint is
violated.
Possible causes include:
The constaint date falls at a time when production is not taking
place.
The capacity is already committed at the constraint date.
The operation was manually rescheduled.
Depending on the cause you can
Change the available capacity
Deallocate other operations that are committed to the capacity
Determine the time of dispatching automatically rather that
manually.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
CY749
- Ordre &, opération & : date de fin limite dépassée ?Get instant SAP help. Sign up for our Free Essentials Plan.
CY748
Ordre &, opération & : date de début limite dépassée
Quelle est la cause de ce problème? Once the operation has been dispatched, the start date constraint is violated. Possible causes include: The con...
CY747
Opé. &, sous-opé. & : poste de travail modifié manuellement
Quelle est la cause de ce problème? The sub-operation was manually dispatched to the work center &V4& or rescheduled to it. The sub-operati...
CY750
Ordre &, opération & : modification des dates impossible (-> statut)
Quelle est la cause de ce problème? You want to reschedule an operation. A system- or user status has been set that prevents this action.Réponse d...
CY751
Ordre &, Opé/phase &, ressource second. & : pas de capacité disponible
Quelle est la cause de ce problème? The system could not find any available capacity within the planning period.Comment corriger cette erreur? Inc...