Message type: E = Error
Message class:  CY - Capacity Requirements Planning 
Message number: 409
Message text: Il n'est pas possible de charger le poste de travail indiqué
You have entered a work center to which the selected operations are to
be dispatched. However, the work center is not in the current selection
of the planning table. But you can only dispatch operations to work
centers that are selected.
You should select one of chosen work centers or call up the planning
table with the selection in which the chosen work center is also
included.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
 Get instant SAP help. Sign up for our Free Essentials Plan.
Get instant SAP help. Sign up for our Free Essentials Plan. 
CY408 Le statut 'chargé' ne peut pas être activé
Message auto-explicatif Étant donné que SAP estime que ce message d'erreur spécifique est 'auto-explicatif', aucune autre information n'a été fou...
CY407 Lot fractionné déjà chargé
Quelle est la cause de ce problème?   You are trying to select and dispatch a split. However this split has already been dispatched.Comment corriger ...
CY410 Quantité de tous lots fractionnés supérieure à quantité de l'opération
Quelle est la cause de ce problème?   You have carried out a quantity split for a capacity requirement. The sum of the quantity to be processed by th...
CY411 La charge de tous les lots est supérieure à la charge de l'opération
Quelle est la cause de ce problème?   You have split the work of some capacity requirements. The sum of the work in the individual splits is greater ...