Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 039
Message text: La contrainte n'a pas pu être respectée
When carrying out scheduling, the system could not keep the time
constraint which you entered for the activity.
Given this situation, if you carry out backward scheduling, you will
get a negative total float.
Check the time constraints entered for the activity.
Check the basic dates for the network in the network header.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
C7039
- La contrainte n'a pas pu être respectée ?Get instant SAP help. Start your 7-day free trial now.
C7038
Conflit de dates : contrainte située trop tard
Quelle est la cause de ce problème? You have maintained a date constraint for the end of the activity. Backward scheduling has determined a latest ...
C7037
Conflit de dates : contrainte située trop tôt
Quelle est la cause de ce problème? The system has carried out forward scheduling and has calculated an earliest date either which is after the tim...
C7040
Conflit de dates : contraintes contradictoires
Quelle est la cause de ce problème? You have entered time contraints for the activity that have caused discrepancies in scheduling. The reasons cou...
C7041
Pas de poste de trav. dans la relation de dép. (tps empl. via calend.rel)
Message auto-explicatif Étant donné que SAP estime que ce message d'erreur spécifique est 'auto-explicatif', aucune autre information n'a été fou...
Cliquez sur ce lien pour rechercher tous les messages SAP.