Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 018
Message text: Le poste de travail en question n'existe pas
The work center that you have specified in the operation does not
exist.
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Check whether you have entered the correct key for the work center.
Change it if necessary.
If you do not change the key for the work center, scheduling is carried
out using either
the calendar that you have maintained in the operation, or
the Gregorian calendar.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
C7018
- Le poste de travail en question n'existe pas ?Get instant SAP help. Start your 7-day free trial now.
C7017
Le calendrier n'a pas été défini
Quelle est la cause de ce problème? You have not defined a calender in the work center nor in the operation.Comment corriger cette erreur? INCLUDE...
C7016
Calendrier non défini
Quelle est la cause de ce problème? You have maintained a calendar which is not defined in the system.Réponse du système Scheduling is carried o...
C7019
Entrée non définie dans la matrice des temps de transport
Quelle est la cause de ce problème? The move time matrix has not been maintained.Réponse du système Scheduling is carried out on the basis of an...
C7020
Dépassement de zone lors du calcul des quantités d'outillages
Quelle est la cause de ce problème? An internal error occurred when calculating the PRT quantity.Réponse du système The field is filled with the...