Do you have any question about this error?
Message type: E = Error
Message class: AO - Appropriation requests - Master data / Customizing
Message number: 263
Message text: &1: &2
For &V1&, the overhead costs (&V2&) are negative. This means that the
plan value for investment costs is greater than the plan value for
combined costs. This is an error, since investment costs are by
definition a part of combined costs.
The system offers an automatic correction option. Choose the 'Correct
plan values' function. Specify whether you want the system to derive
combined costs from the investment costs, or the investment costs from
the combined costs.
&NOTE&
This applies only to those years (overall) for which the overhead costs
are negative.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
AO263
- &1: &2 ?Get instant SAP help. Start your 7-day free trial now.
AO262
Frais généraux négatifs
Quelle est la cause de ce problème? The investment costs are greater than the combined costs. This is not allowed, since the investment costs are s...
AO261
Définition du projet &2 est traitée par l'utilisateur &1
Quelle est la cause de ce problème? Project definition &V2& is blocked by user &V1&. Therefore, appropriation request &V2&,...
AO264
Valeurs de pré-budget cumulées > total valeur pré-budgétée globale
Quelle est la cause de ce problème? The overall plan value is less than the sum of the plan values. The sum of the plan values is the sum of the an...
AO265
&1: &3 > &2
Message auto-explicatif Étant donné que SAP estime que ce message d'erreur spécifique est 'auto-explicatif', aucune autre information n'a été fou...