Do you have any question about this error?
Message type: E = Error
Message class: AJ - Billing program
Message number: 099
Message text: Auc. période de versement partiel valide n'a été déterminée.
A new budget billing plan is to be created for periodic billing. In
this process, an extrapolation is performed for the budget billing
period. &v1& -- &v2& has been determined as the budget billing period,
but this period is invalid. The end (&v2&) of the budget billing period
was determined from the schedule records for meter reading unit &v3&.
Check the schedule records of meter reading unit &v3& for consistency,
and change them if necessary. When doing this, also check the schedule
records of the allocated portion &v4&.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
AJ099
- Auc. période de versement partiel valide n'a été déterminée. ?Get instant SAP help. Start your 7-day free trial now.
AJ098
Document de calcul de fact. &1 pour contrat &2 mis en att. pr vérificat.
Quelle est la cause de ce problème? Document &v1& from contract &v2& has been outsorted because it has not met the requirements of ...
AJ097
Interruption imprévue dans variante &1 du schéma &2.
Quelle est la cause de ce problème? An error has occurred during execution of a variant. Further processing is not possible; billing of the contrac...
AJ100
L'opérande &1 dépend de la saison mais auc. saison n'a été définie.
Quelle est la cause de ce problème? When operand &v1& was defined using Transaction EA51, the indicator for season demand was set. However,...
AJ101
Le nombre de valeurs de pointe de puissance de l'opérande &1 est nul.
Quelle est la cause de ce problème? During preprocessing of demand, the system has determined that no demand peaks have been defined for operand &a...
Cliquez sur ce lien pour rechercher tous les messages SAP.