Do you have any question about this error?
Message type: E = Error
Message class: PPC0 - Messages for PP Confirmation
Message number: 059
Message text: Datos de la orden no son actuales. No se puede realizar la acción
The iPPE master data for order &V1& was changed after the order was
created.
The order data is different to the current iPPE master data, and
therefore it is not possible to automatically assign the order objects
to the reporting points for the current iPPE master data.
The action cannot be executed.
Read the current iPPE master data for the order again, or delete the
order and then subsequently create it again.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
PPC0059
- Datos de la orden no son actuales. No se puede realizar la acción ?Get instant SAP help. Start your 7-day free trial now.
PPC0058
Ya existe una notificación con fecha y hora de registro posteriores
¿Qué causa este problema? To also be able to predict the sequence in which confirmations are created at a later date, the creation time of each con...
PPC0057
Notificación creada demasiado cerca del punto de notificación anterior &1
¿Qué causa este problema? Reporting point &V1& is automatically confirmed when confirming reporting point &V2&. To be able to predi...
PPC0060
Existen varias órdenes para el pedido de cliente. Introduzca una orden
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
PPC0061
Ya se ha confirmado el punto de notificación subsiguiente &1
¿Qué causa este problema? The successor reporting point &V1& has already been confirmed.Respuesta del sistema The confirmation status of t...
Haga clic en este enlace para buscar todos los mensajes de SAP.