Do you have any question about this error?
Message type: E = Error
Message class: KPN - Costing: Networks, Projects
Message number: 051
Message text: Ajuste plan de facturación al componente de material
You have used a unit costing to recalculate the price of the material
component. An invoicing plan with partial invoicing by value has also
been maintained for the material component, but cannot be adjusted
automatically.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Adapt the invoicing plan manually.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
KPN051
- Ajuste plan de facturación al componente de material ?Get instant SAP help. Start your 7-day free trial now.
KPN050
No se transfieren fechas hito en plan facturación para componentes &1, &2
¿Qué causa este problema? The items in the invoiding plan are connected to milestones. The changed milestone dates cannot be adjusted in the invoic...
KPN049
Fechas hito no se transfieren en plan facturación para grafo &1, oper.&2
&Cause& The items in the invoicing plan &V1&, activity &V2&, are linked to milestones. The changed milestones cannot be adapt...
KPN052
Material &1 para elemento PEP &2 ya está valorado
¿Qué causa este problema? Material &V1& has already been valued due to goods being received into stock in WBS element &V2&.Respuest...
KPN053
En proyecto operativo ya se ha realizado una valoración para material &1
¿Qué causa este problema? Material &V1& for WBS element &V2& has been valued in the operative project due to a goods receipt. If yo...
Haga clic en este enlace para buscar todos los mensajes de SAP.