Message text: La operación & no ha podido valorarse dentro del plazo previsto
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
An internal error has occurred.Costing by schedule was not possible for this activity. This may be due
to an error in scheduling or failure to maintain the capacity
requirement distribution key.
In the case of internally-processed activities, valuation is at the
rate for the first period; planned costs are distributed over the whole
duration of the activity. Distribution keys entered in the activity or
the work center are ignored.
Schedule the order again or make sure that the capacity requirement
distribution key is correctly maintained.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
KPN008
- La operación & no ha podido valorarse dentro del plazo previsto ?Get instant SAP help. Start your 7-day free trial now.
KPN007
El plan facturación p.operación & no contiene posic.relevantes p.costes
¿Qué causa este problema? There is an invoicing plan for activity &V1& for which there is no cost-relevant item.Respuesta del sistema Cost...
KPN006
No se ha podido bloquear el grafo &
¿Qué causa este problema? Someone is currently working on network &V1&.Respuesta del sistema The production run does not determine plan da...
KPN009
El plan fact.para componente & no contiene posiciones relev.para costes
¿Qué causa este problema? There is an invoicing plan for component &V1& for which there is no cost-relevant item.Respuesta del sistema Cos...
KPN010
No está permitido actualizar un plan de facturación activo en el doc.
¿Qué causa este problema? The invoicing plan you have chosen as template is already in use in another context - for example, as the invoicing plan ...