Do you have any question about this error?
Message type: E = Error
Message class: FINS_SIS_CUST - Impl. of Doc. Splitting: Customizing
Message number: 115
Message text: Preparativos se deben definir como complet.antes de poder rein.activ.&1
Activities of a project can only be reset if the preparatory phase for
the project has been completed. This is a manual step to set and change
the project status.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
You can check and change the current project status in the Customizing
activity
<DS:SIMG.FINS_MPROJ_RELEAS_06>Complete Preparations</>.
After you have completed the preparatory phase<(>,<)> you can try to
reset activity &V1& again.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
FINS_SIS_CUST115
- Preparativos se deben definir como complet.antes de poder rein.activ.&1 ?Get instant SAP help. Start your 7-day free trial now.
FINS_SIS_CUST114
Preparativos se deben definir como complet.antes de poder ejec.activ.&1
¿Qué causa este problema? Activities of a project can only be run if the preparatory phase for the project has been completed. After the preparator...
FINS_SIS_CUST113
Preparativos se deben definir como completados antes de poder rein.activ.
¿Qué causa este problema? Activities of a project can only be reset if the preparatory phase for the project has been completed. To complete the pr...
FINS_SIS_CUST116
No se puede reinicializar porque no se ha iniciado tratamiento de datos
¿Qué causa este problema? You can only <LS>Reset</> data after data processing has been started and data for reset is available. This i...
FINS_SIS_CUST117
Los preparativos no se pueden completar de nuevo
¿Qué causa este problema? Since preparations for the current project have already been set to completed, it is no longer possible to perform the op...