Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 241
Message text: &1 &2: Fecha fin calculada está en conflicto con fin de restricción
You have defined a finish constraint on a superior project element. The
calculated earliest or latest finish date of the project element &V1&
&V2& violates this constraint.
Example:
The finish constraint <ZK>Must finish on</> is defined with the finish
constraint 4.28. However, the calculated finish date of the task is
4.29.
&V1& &V2& does not have any lower-level project elements, for example,
task without subtasks:
The system transfers the finish date of the constraint from the superior
project element as the corresponding finish date for the project element
&V1& &V2&.
&V1& &V2& does have lower-level project elements, for example, task with
subtasks:
The system does <ZH>not</> transfer the finish date of the constraint
from the superior project element as the corresponding finish date for
the project element &V1& &V2& because this is defined by the lower-level
project elements in bottom-up scheduling.
In <LS>bottom-up scheduling</>, the dates of the superior project
elements are generally specified by the dates of their lower-level
project elements.
Therefore, check the constraint on the superior project element. A
constraint on a lower-level project element can have the same effect.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED240 &1 &2: Fecha de inicio calculada está en conflicto con inicio de restr.
¿Qué causa este problema? You have defined a start constraint on a superior project element. The calculated earliest or latest start date of the pr...
DPR_SHARED239 &1 &2: Una limitación puede ocasionar problemas de programación
¿Qué causa este problema? You have set a constraint on &V1& &V2& and this project element has lower-level project elements, for exa...
DPR_SHARED242 &1 &2: Limitación se encuentra en conflicto con predecesor/sucesor(&3 &4)
¿Qué causa este problema? You have either set a start constraint for the task &V1& &V2& and the constraint date conflicts with the ...
DPR_SHARED243 &1 &2: Solapamiento de fases debido a tarea (&3)
¿Qué causa este problema? You define a constraint or set an actual date for a task which calculates the superior phase in such a way that this phas...
Haga clic en este enlace para buscar todos los mensajes de SAP.