Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 241
Message text: &1 &2: Fecha fin calculada está en conflicto con fin de restricción
You have defined a finish constraint on a superior project element. The
calculated earliest or latest finish date of the project element &V1&
&V2& violates this constraint.
Example:
The finish constraint <ZK>Must finish on</> is defined with the finish
constraint 4.28. However, the calculated finish date of the task is
4.29.
&V1& &V2& does not have any lower-level project elements, for example,
task without subtasks:
The system transfers the finish date of the constraint from the superior
project element as the corresponding finish date for the project element
&V1& &V2&.
&V1& &V2& does have lower-level project elements, for example, task with
subtasks:
The system does <ZH>not</> transfer the finish date of the constraint
from the superior project element as the corresponding finish date for
the project element &V1& &V2& because this is defined by the lower-level
project elements in bottom-up scheduling.
In <LS>bottom-up scheduling</>, the dates of the superior project
elements are generally specified by the dates of their lower-level
project elements.
Therefore, check the constraint on the superior project element. A
constraint on a lower-level project element can have the same effect.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
DPR_SHARED241
- &1 &2: Fecha fin calculada está en conflicto con fin de restricción ?Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED240
&1 &2: Fecha de inicio calculada está en conflicto con inicio de restr.
¿Qué causa este problema? You have defined a start constraint on a superior project element. The calculated earliest or latest start date of the pr...
DPR_SHARED239
&1 &2: Una limitación puede ocasionar problemas de programación
¿Qué causa este problema? You have set a constraint on &V1& &V2& and this project element has lower-level project elements, for exa...
DPR_SHARED242
&1 &2: Limitación se encuentra en conflicto con predecesor/sucesor(&3 &4)
¿Qué causa este problema? You have either set a start constraint for the task &V1& &V2& and the constraint date conflicts with the ...
DPR_SHARED243
&1 &2: Solapamiento de fases debido a tarea (&3)
¿Qué causa este problema? You define a constraint or set an actual date for a task which calculates the superior phase in such a way that this phas...