Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 236
Message text: &1 &2 > &3 &4: Conflicto con restricciones
You have defined a constraint for the project element <(>&<)>V2& (
<(>&<)>V1&). However, this constraint shifts the project element
<(>&<)>V4& (<(>&<)>V3&) on the time line so that it overlaps
with a predecessor or successor or is before the fixed start date or
fixed finish date of the project.
<ZU>Example:</>
Two phases P1 and P2 are linked by a relationship with a <ZH>positive</>
lag. You set the <ZK>Must start on</> constraint for a task that belongs
to phase P2 and the constraint date is before the finish date of phase
P1. This causes an overlap between the phases P1 and P2.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
The system resolves this scheduling conflict by resetting the constraint
dates for the project element <(>&<)>V2& (<(>&<)>V1&).
Check the relationships for the project element <(>&<)>V4& (
<(>&<)>V3&). Adjust the relationships accordingly. If you want the
project elements to overlap, define relationships with a <ZH>negative</>
lag.
The project element <(>&<)>V4& (<(>&<)>V3&) is a phase:
Do not allow phases to overlap; the phase concept works on the basis
that phases are disjoint.
The project element <(>&<)>V4& (<(>&<)>V3&) is the project
definition:
Set the constraints on the project element <(>&<)>V4& (<(>&<)>V3
&) accordingly or adjust the constraints on the project
definition.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
DPR_SHARED236
- &1 &2 > &3 &4: Conflicto con restricciones ?Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED235
Conflicto fecha de fin fija con final de marco temporal (fase/proyecto)
¿Qué causa este problema? A finish constraint was entered for the checklist item. The checklist that belongs to the checklist item is defined below...
DPR_SHARED234
Se ha efectuado la programación descendente
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
DPR_SHARED237
&1 &2: Inicio calculado se encuentra fuera del marco temporal indicado
¿Qué causa este problema? The start date for the project element &V1& &V2& that was determined using the relationships is before th...
DPR_SHARED238
El status predecesor/sucesor no permite ninguna relación de orden
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
Haga clic en este enlace para buscar todos los mensajes de SAP.