Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 212
Message text: &1 &2: Fecha final restricción en conflicto con fecha de fin determinada
A constraint is set for the finish of the project element. In backward
scheduling, the system calculates the finish (latest finish) of the
project element step by step:
Actual finish of the project element (you can use the BAdI to ignore
this).
If no actual finish has been set, the system determines it from the
successor relationships of the project element.
If no actual finish was found in the previous steps, the system takes
the finish of the higher-level project element.
The system then compares the determined finish (latest finish) with the
constraint for the finish. The warning appears if the finish conflicts
with the constraint for the finish.
The system sets the finish of the constraint as the calculated finish.
Check whether the constraint for the finish is realistic.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
DPR_SHARED212
- &1 &2: Fecha final restricción en conflicto con fecha de fin determinada ?Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED211
&1 &2: Fecha de inicio restricc.en conflicto con fecha inicio determinada
¿Qué causa este problema? A constraint is set for the start of the project element. In forward scheduling, the system calculates the start (earlies...
DPR_SHARED210
Sin autorización para programar &1 "&2"
¿Qué causa este problema? You do not have sufficient authorization to carry out scheduling for &V1& '&V2&'.Respuesta del ...
DPR_SHARED213
&1 &2: Restricc.fecha inicial en conflicto con el fin del marco temporal
¿Qué causa este problema? The system calculated a finish date using the fixed start date and the duration of the project element. This finish date ...
DPR_SHARED214
&1 &2: Restricc.fecha final en conflicto con el inicio del marco temporal
¿Qué causa este problema? The system calculated a start date using the fixed finish date and the duration of the project element. This fixed start ...
Haga clic en este enlace para buscar todos los mensajes de SAP.