Message text: Asign.recursos: Gasto asignado excesivo p.horas de trabajo disponibles
The assigned effort defined for the assignment of role &V1& to resource
&V2& is higher than the maximum working time available that was
determined by the validity period &V3&.
The following applies for the maximum working time available:
Each day is estimated as 24 hours
The Gregorian calendar applies, that is, the system does not
differentiate between working days and non-working days
A single resource is used in the calculation, that is, the maximum
possible Gregorian working time is available once
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Check and correct the assigned effort or the validity of the resource
assignment.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
DPR_BUPA_LINK006
- Asign.recursos: Gasto asignado excesivo p.horas de trabajo disponibles ?Get instant SAP help. Start your 7-day free trial now.
DPR_BUPA_LINK005
Asignación recursos no se encuentra en el ámbito de validez del rol
¿Qué causa este problema? The validity &V3& of resource &V2& is not entirely within the validity period &V4& of role &V...
DPR_BUPA_LINK004
Solapamiento de asignaciones recursos
¿Qué causa este problema? The validity period &V3& for the assignment of role &V1& and '&V2&' overlaps with the v...
DPR_BUPA_LINK007
Indique un interlocutor comercial válido
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
DPR_BUPA_LINK008
La ocupación ya tiene asignado un recurso
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
Haga clic en este enlace para buscar todos los mensajes de SAP.