Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 421
Message text: Ya se ha partido la necesidad de capacidades
You are trying to allocate a capacity requirement directly to an
individual capacity. With this capacity requirement you are not dealing
with a split; however, the requirement has already been split.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
You can only allocate a capacity requirement directly to an individualThe allocation is terminated.
If you want to split or allocate a capacity requirement you can do this
on the dialog box "Split/allocate".
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CY421
- Ya se ha partido la necesidad de capacidades ?Get instant SAP help. Start your 7-day free trial now.
CY420
Las fases no se pueden planificar o no pueden ser anuladas de la planif.
¿Qué causa este problema? Currently you cannot dispatch phases directly.¿Cómo arreglar este error? If you want to dispatch or deallocate phases,...
CY419
Entre un grupo o bien un grupo 0, o bien un grupo distinto de 0
¿Qué causa este problema? You have made entries both with the group 0 as well as with one or more groups not equal to 0. However this is not possib...
CY422
En la fecha indicada no es válida la persona seleccionada
¿Qué causa este problema? The person is not working at the work center at the date selected.¿Cómo arreglar este error? Choose another date.Extra...
CY423
Error en la programación de la partición &
¿Qué causa este problema? While trying to schedule split number & an error arose. A possible cause of the error is the non-availability of the ...