How To Fix CY298 - Nec.capacidad/Capacidad no existen o no relevantes p.progr.capacidades


CY298 - Overview

  • Message type: E = Error

  • Message class: CY - Capacity Requirements Planning

  • Message number: 298

  • Message text: Nec.capacidad/Capacidad no existen o no relevantes p.progr.capacidades

  • Show details Hide details
  • ¿Qué causa este problema?

    In the capacity availability check either no capacities were found or
    none were found that were relevant for finite scheduling or no capacity
    requirements were found.
    The possible causes are:
    no capacities have been assigned to the work centers checked
    in the capacities at the work centers checked the indicator
    <ls>Relevant to finite scheduling</> is not set. Thus the capacities
    can have an unlimited load.
    no capacity requirements exist for the order checked
    &System_response&
    The capacity availability is checked.

    ¿Cómo arreglar este error?

    Assign capacities to the work centers affected by the order.
    Set the indicator <ls>Relevant to finite scheduling</> at the
    capacities in the work centers affected.
    Find out why no capacity requirements exist and, if possible, solve the
    problem.
    Carry out the capacity availability check again.

    Extracto de mensaje de error del sistema SAP. Copyright SAP SE.


CY298 - Details








Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Mensajes de error de SAP relacionados

Haga clic en los enlaces a continuación para ver los siguientes mensajes relacionados:

Haga clic en este enlace para buscar todos los mensajes de SAP.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker