How To Fix CNIF_PI035 - Se utiliza más de un proyecto


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CNIF_PI - BAPI Notifications of Project System

  • Message number: 035

  • Message text: Se utiliza más de un proyecto

  • Show details Hide details
  • ¿Qué causa este problema?

    You have called one of the individual BAPIs listed below. As a result,
    however, more than one project is being used in the current LUW
    (logical unit of work). This is not allowed for data consistency
    reasons.

    El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.

    Individual BAPIs:
    Method ProjectDefinitionPI:
    BAPI Method
    BAPI_BUS2001_CREATE ProjectDefinitionPI.CreateSingle
    BAPI_BUS2001_CHANGE ProjectDefinitionPI.Change
    BAPI_BUS2001_DELETE ProjectDefinitionPI.Delete
    BAPI_BUS2001_SET_STATUS ProjectDefinitionPI.SetStatus
    Method WBSPI:
    BAPI Method
    BAPI_BUS2054_CREATE_MULTI WBSPI.CreateMultiple
    BAPI_BUS2054_CHANGE_MULTI WBSPI.ChangeMultiple
    BAPI_BUS2054_DELETE_MULTI WBSPI.DeleteMultiple
    BAPI_BUS2001_SET_STATUS WBSPI.SetStatus
    Method NetworkPI
    BAPI Method
    BAPI_BUS2002_CREATE NetworkPI.CreateFromData
    BAPI_BUS2002_CHANGE NetworkPI.Change
    BAPI_BUS2002_DELETE NetworkPI.Delete
    BAPI_BUS2002_ACT_CREATE_MULTI NetworkPI.ActCreateMultiple
    BAPI_BUS2002_ACT_CHANGE_MULTI NetworkPI.ActChangeMultiple
    BAPI_BUS2002_ACT_DELETE_MULTI NetworkPI.ActDeleteMultiple
    BAPI_BUS2002_ACTELEM_CREATE_M NetworkPI.ActElemCreateMultiple
    BAPI_BUS2002_ACTELEM_CHANGE_M NetworkPI.ActElemChangeMultiple
    BAPI_BUS2002_ACTELEM_DELETE_M NetworkPI.ActElemDeleteMultiple
    BAPI_BUS2002_SET_STATUS NetworkPI.SetStatus
    One or more of the above individual BAPIs can be called within a LUW.
    You finish the current LUW by calling the BAPIs "BAPI_PS_PRECOMMIT "
    and "BAPI_TRANSACTION_COMMIT", in that order.
    Afterwards, you can start a new LUW by calling up the individual BAPIs
    again.
    More than one project is used, for example, if
    You create or change more than one project
    You have changed a project and want to change a network to which WBS
    elements from a different project are assigned
    You want to change various networks to which WBS elements from
    different projects are assigned
    You create or change a WBS assignment in a network so that a WBS
    element from a second project is used
    WBS elements from different projects are already assigned to a network
    (note: this type of network can never be processed with the above
    mentioned network individual BAPIs)

    Respuesta del sistema

    The current individual BAPI is not executed.

    ¿Cómo arreglar este error?

    You are probably using a self-developed report. In this case, notify
    the developer responsible for the report.
    The report may only use a maximum of one project per LUW! If required,
    the individual BAPI calls must be distributed between more than one
    LUW.

    Procedimiento para Administradoras de Sistemas


    Extracto de mensaje de error del sistema SAP. Copyright SAP SE.


Smart SAP Assistant

  • ¿Cuál es la causa y la solución del error de SAP CNIF_PI035 - Se utiliza más de un proyecto ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Mensajes de error de SAP relacionados

Haga clic en los enlaces a continuación para ver los siguientes mensajes relacionados:

Haga clic en este enlace para buscar todos los mensajes de SAP.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker