Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 836
Message text: La duración no puede convertirse a la unidad deseada
You have selected different units for work and duration when
calculating duration.
In this case, the calculated value for duration will be either too
small or too large to be displayed correctly. When the duration is too
small or less than 0.0, it will be displayed as 0. When the
duration is too large or greater than 9999.9, the system also
cannot display the correct duration.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
Select a different unit to display duration.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CN836
- La duración no puede convertirse a la unidad deseada ?Get instant SAP help. Start your 7-day free trial now.
CN835
El trabajo no puede convertirse a la unidad deseada
¿Qué causa este problema? You have selected different units for calculation the work and the duration. In this case, the calculated value of work w...
CN834
En el perfil de grafo & no se ha grabado ningún perfil de gráfico
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
CN837
REO entre operaciones en alternativas diferentes no están permitidas
¿Qué causa este problema? You have entered a relationship to another alternative of the standard network. This is not allowed.Respuesta del sistema...
CN838
Existen varias operaciones de salida/meta
¿Qué causa este problema? The network which is to become a subnetwork has several start and/or finish (target) activities. In this situation, the s...