Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 682
Message text: La posición de fecha liberación &1 operación &2 está &3 días en el pasado
You have triggered the creation of a purchase requisition. The system
determines the release date as the difference between the delivery date
and the total derived from the planned delivery time, the goods receipt
processing time, and the processing time in Purchasing.
The release date is in the past. Since it is not possible for the
release to be earlier than the current date, the system assigns the
current date to the release date.
Check the relevant data for the delivery date and the release date.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CN682
- La posición de fecha liberación &1 operación &2 está &3 días en el pasado ?Get instant SAP help. Start your 7-day free trial now.
CN681
Fecha de necesidad de la posición & se encuentra en el pasado
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
CN680
Indique una fecha de necesidad
¿Qué causa este problema? You have set the indicator <LS>Manual reqmts. date</> however, you have not entered a requirements date.¿Có...
CN683
Los datos de compras para componente &1, operación &2 están incompletos
¿Qué causa este problema? You want to release an activity. You have allocated one or more externally procured material components to the activity. ...
CN684
La operación & no ha sido liberada -> ver log
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
Haga clic en este enlace para buscar todos los mensajes de SAP.