Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 079
Message text: Los centros de beneficio de los elementos PEP deben concordar
A. You want to change the WBS element of a component.
Profit Center Accounting is active within the scheduled network dates
for the controlling area of the WBS elements. The WBS element you
entered is assigned to a different profit center than the original WBS
element.
B. You want to reallocate a component that is assigned to a WBS element
to another activity.
Profit Center Accounting is active within the scheduled network dates
for the controlling area of the WBS elements. The WBS element of the
component is assigned to a different profit center than the target
activity's WBS element.
A. Choose a WBS element with the same profit center.
B. Choose an activity with a WBS element from the same profit center.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CN079
- Los centros de beneficio de los elementos PEP deben concordar ?Get instant SAP help. Start your 7-day free trial now.
CN078
Las divisiones de los elementos PEP deben concordar
¿Qué causa este problema? A. You want to change the WBS element of a component. The business area balance sheet is active for the company code of t...
CN077
Las sociedades de los elementos PEP deben concordar
¿Qué causa este problema? A. You want to change the WBS element of a component. The WBS element you entered is assigned to a different company code...
CN080
El status del elemento PEP & no permite asignación
¿Qué causa este problema? You want to assign a WBS element. The WBS element has one of the following statuses: marked for deletion deleted technica...
CN081
Elemento PEP & no es elemento de imputación (verificar)
¿Qué causa este problema? You want to settle the costs for material components to a WBS element. However, the WBS element which you entered is not ...
Haga clic en este enlace para buscar todos los mensajes de SAP.