Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 016
Message text: El elemento PEP &1 para la operación &2 no se ha liberado (parcialmente)
You want to release an activity that is allocated to WBS element &V1&,
or you want to allocate an activity to WBS element &V1& after the
activity has been released. However, the system status of the WBS
element is neither <ls>released</> nor <ls>partially released</>.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
Set the system status of WBS element &V1& to <ls>released</>, then
release the activity or assign the WBS element to the activity.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CN016
- El elemento PEP &1 para la operación &2 no se ha liberado (parcialmente) ?Get instant SAP help. Start your 7-day free trial now.
CN015
Se ha liberado la operación &
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
CN014
El elemento PEP &1 para grafo/orden &2 no se ha liberado (parcialmente)
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
CN017
No se ha liberado (parcialmente) la definición del proyecto &
¿Qué causa este problema? You cannot release the network because the project definition &V1& that is assigned to it does not have the syste...
CN018
Imputación de operación: visualización de costes a través de la operación
¿Qué causa este problema? This network has activity account assignment. That means you can only display costs using the menu <LS>Edit -> C...
Haga clic en este enlace para buscar todos los mensajes de SAP.