Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 565
Message text: El planificador de necesidades &2 no existe en el centro &1
The MRP controller &v2&, who you entered in the newtwork profile, does
not work in plant &v1&. Therefore you cannot create activities for the
WBS element.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Enter a correct MRP controller in the network profile.
Choose <ls>Settings -> Options</> and change the MRP controller on the
"Control" tab page.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CJ565
- El planificador de necesidades &2 no existe en el centro &1 ?Get instant SAP help. Start your 7-day free trial now.
CJ564
Indique la fecha de inicio y la fecha de fin
¿Qué causa este problema? You have only entered one date for the WBS element (either the start or the finish date) however both dates are required ...
CJ563
La fecha fin es anterior a la fecha inicio
¿Qué causa este problema? You entered a finish date for the WBS element that is earlier than the start date of the WBS element.Respuesta del sistem...
CJ566
No se puede determinar el centro. Repase el perfil
¿Qué causa este problema? You have entered a key for a plant in the project profile which the system does not recognize.Respuesta del sistema INCL...
CJ567
No se puede notificar el elemento PEP
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
Haga clic en este enlace para buscar todos los mensajes de SAP.