How To Fix CJ441 - Tratar la asignación de proyectos parciales completamente.


CJ441 - Overview

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 441

  • Message text: Tratar la asignación de proyectos parciales completamente.

  • Show details Hide details
  • ¿Qué causa este problema?

    You have assigned individual WBS elements to subprojects; however, you
    must assign <ZH>each</> WBS element to a subproject in order to have an
    accurate evaluation in the project information system.

    Respuesta del sistema

    If you are working with a standard WBS this is only an informational
    message. The system will still save the WBS.
    If you are working with a operative work breakdown structure the system
    will not save the WBS.

    ¿Cómo arreglar este error?

    Change the assignments to subprojects. To do this, on the detail
    screens, select the <LS>Organisation</> tab page and either assign
    every WBS element to a subproject or remove the subproject assignment
    from the individual WBS elements.

    Extracto de mensaje de error del sistema SAP. Copyright SAP SE.


Smart SAP Assistant

  • ¿Cuál es la causa y la solución del error de SAP CJ441 - Tratar la asignación de proyectos parciales completamente. ?







Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Mensajes de error de SAP relacionados

Haga clic en los enlaces a continuación para ver los siguientes mensajes relacionados:

Haga clic en este enlace para buscar todos los mensajes de SAP.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author