Message text: ¿Fecha de entrega de material & aceptable? Fecha realista: &
The date is the delivery date taking int account
<GL:planned_delivery_time>planned delivery time</> in the
<GL:material_master>material master</>
purchasing department processing time from table 399D
goods receipt processing time in the material master or in the item
INCLUDE NA_T160M
You can change the delivery date specified and enter a realistic
delivery date &V2&.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
C7068
- ¿Fecha de entrega de material & aceptable? Fecha realista: & ?Get instant SAP help. Start your 7-day free trial now.
C7067
No se han actualizado todos los valores prefijados
¿Qué causa este problema? You have not maintained all standard values in the operation.¿Cómo arreglar este error? Maintain the standard values i...
C7066
Error en la programación de particiones
¿Qué causa este problema? An error occurred when attempting to schedule a split of an operation. The cause of the error may be that a person is not...
C7069
MAF: no se ha encontrado ningún registro maestro
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
C7070
REO: no se ha podido respetar duración máxima
¿Qué causa este problema? A maximum duration has been entered for the relationship between order &V1&, operation &V2& and order &am...