Message type: E = Error
Message class: AO - Appropriation requests - Master data / Customizing
Message number: 336
Message text: Variante &3: Inicio de realización &1 después de fecha de terminación &2
Implementation start date &V1& that was entered is after the completion
date &V2& of variant &V3&. The implementation start date always has to
be before the completion date (&V2&).
The entry is not allowed.
Do one of the following:
Correct implementation start date &V1& that you entered so that it is
before or the same date as completion date &V2&.
Correct completion date &V2&, so that it is after or the same date as
implementation start date &V1&.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
Get instant SAP help. Sign up for our Free Essentials Plan.
AO335 Variante &3: Fecha terminación &1 después de entrada en productivo &2
¿Qué causa este problema? Completion date &V1& that was entered is after the startup date &V2& of the variant. The completion date ...
AO334 El proceso "&2" no se puede ejecutar debido a la alternativa
¿Qué causa este problema? Appropriation request &V1& is being submitted for approval. One of the alternate requests for this appropriation ...
AO337 Variante &3: Inicio realización &1 tras puesta en servicio &2.
¿Qué causa este problema? Implementation start date &V1& that was entered is after the startup date &V2& of variant &V3&. T...
AO338 Indique un número
¿Qué causa este problema? You did not enter a number for the decimal places. The value range is between 0 and 9.Respuesta del sistema The report i...