Message type: E = Error
Message class: V5 - Contract processing
Message number: 009
Message text: The determined date & deviates from the specified contract start date
The system compared the contract start date with the date determined by
the corresponding rule for contract start and found that they are not
the same.
The system will not allow any further processing.
You can either delete the contract start rule, in order to copy the
contract start that was manually entered, or you can delete the
contract start date so that the date generated by the rule is copied.
Error message extract from SAP system. Copyright SAP SE.
V5009
- The determined date & deviates from the specified contract start date ?Get instant SAP help. Start your 7-day free trial now.
V5008
The baseline date for rule & is initial: determination not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
V5007
The baseline date for contract start date rule & has not been specified
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
V5010
Rule & has the contract start or end date as its baseline date
What causes this issue? The system tried to determine the contract start date according to the rule and found that the contract start date has been d...
V5011
Neither a baseline date nor a calendar ID has been specified for Rule &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...