Do you have any question about this error?
Message type: E = Error
Message class: /SAPAPO/RRP_HEUR -
Message number: 608
Message text: &3 days cannot be added to the date &2 using calendar &1
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/RRP_HEUR608
- &3 days cannot be added to the date &2 using calendar &1 ?The SAP error message
/SAPAPO/RRP_HEUR608
typically occurs in the context of Advanced Planning and Optimization (APO) when there is an issue with date calculations related to the planning calendar. The message indicates that a certain number of days (in this case, 3 days) cannot be added to a specified date using a specified calendar.Cause:
- Calendar Configuration: The calendar being used may not have the necessary working days defined for the period in question. For example, if the calendar does not include weekends or holidays, adding days may exceed the available working days.
- Date Validity: The date to which you are trying to add days may be at the end of a planning horizon or outside the valid range of the calendar.
- Planning Area Settings: The planning area settings may restrict the addition of days based on certain criteria or configurations.
Solution:
Check Calendar Settings:
- Go to the transaction code
/SAPAPO/MC62
to check the calendar settings.- Ensure that the calendar has the correct working days and holidays defined for the period you are working with.
Review Date Validity:
- Verify the date you are trying to use. Ensure it falls within the valid range of the calendar and the planning horizon.
- If the date is at the end of the planning horizon, consider extending the planning horizon if necessary.
Adjust Planning Area Settings:
- Review the settings of the planning area to ensure that there are no restrictions that would prevent the addition of days.
- Check if there are any specific rules or configurations that might be affecting the date calculations.
Use Alternative Dates:
- If the current date cannot accommodate the addition of days, consider using an alternative date that is valid within the calendar.
Consult Documentation:
- Refer to SAP documentation or help resources for more detailed information on calendar configurations and date handling in APO.
Related Information:
/SAPAPO/MC62
(Maintain Calendar) and /SAPAPO/MC73
(Display Calendar).By following these steps, you should be able to identify the cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
/SAPAPO/RRP_HEUR607
BAdI implementation for pegging horizons provides no values
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
/SAPAPO/RRP_HEUR606
Pegging horizon &1 is not supported
What causes this issue? The pegging horizon &V1& is not supported.System Response This means that the heuristic cannot be executed.How to fi...
/SAPAPO/RRP_HEUR609
No ATP checking horizon is defined for product &1 in location &2
What causes this issue? The <DS:DE./SAPAPO/CHKHOR>ATP checking horizon</> has not been defined for product &V1& in location &...
/SAPAPO/RRP_HEUR610
The ATP checking horizon is zero days for product &1 in location &2
What causes this issue? The <DS:DE./SAPAPO/CHKHOR>ATP checking horizon</> for product &V1& in location &V2& is zero days....
Click on this link to search all SAP messages.