Message text: You are not allowed to schedule operations in non-working times
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/RRP_ATP152
- You are not allowed to schedule operations in non-working times ?The SAP error message
/SAPAPO/RRP_ATP152
indicates that there is an attempt to schedule operations during non-working times in the Advanced Planning and Optimization (APO) module. This typically occurs when the planning process tries to allocate resources or schedule production activities outside of the defined working hours.Cause:
- Non-Working Time Configuration: The system has been configured with specific working times for resources (e.g., machines, labor) and the operation being scheduled falls outside these defined hours.
- Resource Availability: The resource may not be available during the requested time due to maintenance, holidays, or other non-working periods.
- Planning Calendar: The planning calendar may not align with the operational calendar, leading to scheduling conflicts.
Solution:
Check Resource Working Times:
- Go to the resource master data and verify the working times defined for the resource in question. Ensure that the operation is scheduled within these times.
- Adjust the working times if necessary to accommodate the scheduling needs.
Adjust Planning Parameters:
- Review the planning parameters and settings in the APO system to ensure they align with the operational requirements.
- If the operation needs to be scheduled during non-working times, consider adjusting the planning parameters to allow for flexibility.
Modify the Operation Schedule:
- If possible, reschedule the operation to fall within the defined working hours.
- Use the planning board or other scheduling tools to find an appropriate time slot.
Review the Planning Calendar:
- Ensure that the planning calendar used in the APO system matches the operational calendar. If there are discrepancies, update the planning calendar accordingly.
Consult Documentation:
- Refer to SAP documentation or help resources for more detailed guidance on configuring working times and scheduling operations.
Related Information:
/SAPAPO/RRP3
(Product View) or /SAPAPO/RRP4
(Resource View) to analyze the scheduling and resource allocation.By following these steps, you should be able to resolve the error and successfully schedule operations within the allowed working times.
Get instant SAP help. Start your 7-day free trial now.
/SAPAPO/RRP_ATP151
The planning direction of strategy no. &1 of &2 is not suitable for CTP
What causes this issue? The planning direction in the strategy number &V1& of the selected strategy profile &V2& is not suitable for ...
/SAPAPO/RRP_ATP150
The planning mode of strategy no. &1 of &2 is not suitable for CTP
What causes this issue? Strategy profile for CTP: The planning mode of the stategy number &V1& of the selected strategy profile &V2& ...
/SAPAPO/RRP_ATP153
PP/DS finite bucket planning with campaign conditions not allowed
What causes this issue? In strategy number &V1& of the strategy profile &V2&, you have set the indicator <LB>Consider Campaign ...
/SAPAPO/RRP_ATP154
Fixed and dynamic pegging relationships are not considered
What causes this issue? In the strategy number &V1& of the strategy profile &V2&, you have set the indicator <LB>Consider Fixed...
Click on this link to search all SAP messages.