Message type: E = Error
Message class: /SAPAPO/PPM_MAINTAIN -
Message number: 508
Message text: Only link type end-start for successor of setup activity &1 &2 allowed
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/PPM_MAINTAIN508
- Only link type end-start for successor of setup activity &1 &2 allowed ?The SAP error message
/SAPAPO/PPM_MAINTAIN508
indicates that there is an issue with the link type defined for a successor of a setup activity in the Production Planning and Detailed Scheduling (PP/DS) module of SAP Advanced Planning and Optimization (APO). Specifically, the error states that only the "end-start" link type is allowed for successors of setup activities.Cause:
This error typically occurs when:
- You are trying to create a successor activity for a setup activity using a link type other than "end-start." In PP/DS, setup activities must be followed by successor activities that start after the setup activity has ended.
- The configuration or planning setup in your system does not adhere to the required constraints for setup activities.
Solution:
To resolve this error, you can take the following steps:
Check Link Types: Review the link types defined for the activities in question. Ensure that the successor activity is linked to the setup activity using the "end-start" link type. This means that the successor activity should start only after the setup activity has completed.
Modify Activity Relationships:
- Go to the relevant planning board or transaction where you manage the activities.
- Identify the setup activity and its successor.
- Change the link type to "end-start" if it is currently set to a different type (e.g., "start-start," "end-end," etc.).
Review Planning Parameters: Ensure that the planning parameters and settings for the production process are correctly configured to allow for the required link types.
Consult Documentation: If you are unsure about how to change the link types or if the error persists, refer to the SAP documentation or help resources for guidance on managing activity relationships in PP/DS.
Testing: After making the necessary changes, test the planning scenario again to ensure that the error no longer occurs.
Related Information:
By following these steps, you should be able to resolve the error and ensure that your setup activities and their successors are correctly linked in your planning process.
Get instant SAP help. Start your 7-day free trial now.
/SAPAPO/PPM_MAINTAIN507
Setup activity &1 &2 has a predecessor activity in the same operation
What causes this issue? A setup activity cannot have a predecessor activity in the same operation.System Response The system issues an error message...
/SAPAPO/PPM_MAINTAIN506
Activity &1 &2 contains no mode that can be selected automatically
What causes this issue? Activity does not contain a mode that can be automatically selected.System Response The system issues an error message and w...
/SAPAPO/PPM_MAINTAIN509
An internal material flow has been modeled for the product &1
What causes this issue? The product is both produced by this PPM and is used in another activity. This type of modeling is generally known as "I...
/SAPAPO/PPM_MAINTAIN510
The activities in operation &1 were no linked in a linear form
What causes this issue? Some activities in the operation were networked in parallel. This is not allowed.System Response The system issues an error ...