How To Fix /SAPAPO/PMAN011 - Backward scheduling of the critical path from &1


SAP Error Message - Details

  • Message type: E = Error

  • Message class: /SAPAPO/PMAN -

  • Message number: 011

  • Message text: Backward scheduling of the critical path from &1

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message /SAPAPO/PMAN011 - Backward scheduling of the critical path from &1 ?

    The SAP error message /SAPAPO/PMAN011 typically relates to issues in the backward scheduling process within the SAP Advanced Planning and Optimization (APO) module. This error indicates that there is a problem with the critical path scheduling for a specific production order or planning object.

    Cause:

    The error message /SAPAPO/PMAN011 can be triggered by several factors, including:

    1. Missing or Incomplete Data: Required data for backward scheduling may be missing or incomplete, such as lead times, production resources, or dependencies between operations.

    2. Scheduling Constraints: There may be constraints in the scheduling process, such as resource availability, capacity issues, or conflicting orders that prevent the system from calculating a valid schedule.

    3. Incorrect Configuration: The configuration settings for the planning area or the production process may not be set up correctly, leading to issues in scheduling.

    4. Critical Path Issues: The critical path may not be defined correctly, or there may be issues with the relationships between tasks that affect the scheduling.

    Solution:

    To resolve the error, consider the following steps:

    1. Check Data Completeness: Ensure that all necessary data for the production order or planning object is complete. This includes checking lead times, resource availability, and any dependencies between operations.

    2. Review Scheduling Parameters: Examine the scheduling parameters and constraints in the APO system. Make sure that the settings align with the production process and that there are no conflicting constraints.

    3. Analyze the Critical Path: Investigate the critical path for the production order. Ensure that all tasks are correctly defined and that there are no missing relationships or dependencies.

    4. Adjust Resource Allocation: If resource availability is an issue, consider adjusting the allocation of resources or modifying the production schedule to accommodate the constraints.

    5. Consult Documentation: Refer to SAP documentation or support notes related to the error message for additional insights and troubleshooting steps.

    6. Testing and Simulation: If possible, run simulations or tests in a development environment to identify the root cause of the issue without affecting live operations.

    Related Information:

    • SAP Notes: Check for any relevant SAP Notes that may provide additional context or solutions for this specific error message.
    • APO Configuration: Review the configuration settings in the APO system, particularly those related to production planning and scheduling.
    • User Forums and Communities: Engage with SAP user communities or forums where similar issues may have been discussed, and solutions shared.

    If the issue persists after following these steps, it may be beneficial to involve your SAP support team or a consultant with expertise in SAP APO for further assistance.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant