Message text: Resources were adjusted for &1 plan/process orders
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/CDPSHEURIST017
- Resources were adjusted for &1 plan/process orders ?The SAP error message
/SAPAPO/CDPSHEURIST017
indicates that resources were adjusted for a specific plan or process orders in the SAP Advanced Planning and Optimization (APO) module. This message typically arises during the planning process when the system attempts to optimize resource allocation based on the constraints and requirements defined in the planning scenario.Cause:
- Resource Constraints: The error may occur due to insufficient resources (e.g., machines, labor) to meet the demand for production orders or planned orders.
- Capacity Planning Issues: If the capacity of resources is not properly defined or if there are conflicting capacity requirements, the system may need to adjust resources to align with the planned orders.
- Heuristic Settings: The heuristic used for planning may have specific settings that lead to resource adjustments, especially if the heuristic is designed to optimize resource utilization.
- Order Prioritization: If there are multiple orders competing for the same resources, the system may adjust resources to prioritize certain orders based on predefined criteria.
Solution:
- Review Resource Availability: Check the availability of resources in the system. Ensure that the capacity of resources is sufficient to meet the demand.
- Adjust Capacity Settings: If necessary, adjust the capacity settings for the resources in the planning book or master data to ensure they reflect realistic production capabilities.
- Heuristic Configuration: Review the configuration of the heuristic being used. Ensure that it is set up correctly to handle the specific requirements of your planning scenario.
- Order Management: Analyze the orders that are causing the adjustments. You may need to prioritize certain orders or reschedule them based on resource availability.
- Run Planning Again: After making the necessary adjustments, rerun the planning process to see if the issue persists.
Related Information:
/SAPAPO/MC90
(to check the planning book) or /SAPAPO/CDPSHEUR
(to run heuristics) to analyze the situation further.By following these steps, you should be able to identify the root cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
/SAPAPO/CDPSHEURIST016
Resource adjustment not necessary; Res corresponds to res. dependencies
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
/SAPAPO/CDPSHEURIST015
No def. in the ResProfile for the selected resource; function terminated
What causes this issue? None of the resources you selected has been defined in the resource profile. The <DS:TX./SAPAPO/CDPS_HEURIST>correction...
/SAPAPO/CDPSHEURIST018
Order &1 not adjusted; resource &2 has no usable alternative resources
What causes this issue? The system has executed the <DS:TX./SAPAPO/CDPS_HEURIST>correction heuristic for automatic resource selection</> ...
/SAPAPO/CDPSHEURIST019
Order &1 could not be rescheduled on resource &2; scheduling problem
What causes this issue? The <DS:TX./SAPAPO/CDPS_HEURIST>correction heuristic for automatic resource selection</> was executed. However, t...