How To Fix RSH_LVLING_CONFLICTS503 - &1: Operation ends after target week


RSH_LVLING_CONFLICTS503 - Overview

  • Message type: E = Error

  • Message class: RSH_LVLING_CONFLICTS - Leveling Conflicts (Business Messages)

  • Message number: 503

  • Message text: &1: Operation ends after target week

  • Show details Hide details
  • What causes this issue?

    There's not enough capacity in the work center to schedule the entire
    operation for this week.

    System Response

    The app schedules part of the operation for this week and another part
    for next week, without checking next week's capacity.

    How to fix this error?

    Make sure to check next week's capacity and adjust the operation dates
    if required.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message RSH_LVLING_CONFLICTS503 - &1: Operation ends after target week ?
    The SAP error message RSH_LVLING_CONFLICTS503 typically occurs in the context of SAP's planning and scheduling functionalities, particularly when dealing with leveling conflicts in project management or production planning. The message indicates that an operation cannot be scheduled or leveled because it extends beyond the target week defined in the planning parameters.
    
    Cause: The error is generally caused by one of the following issues: Scheduling Constraints: The operation you are trying to schedule has constraints that prevent it from being completed within the defined target week. Resource Availability: The resources required for the operation may not be available during the target week, leading to a conflict. Incorrect Planning Parameters: The target week may be set incorrectly in the planning parameters, or the operation's duration may exceed the available time frame. Dependencies and Predecessors: There may be dependencies or predecessor tasks that are not completed, which can delay the operation beyond the target week.
    Solution: To resolve the error, you

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker