Do you have any question about this error?
Message type: E = Error
Message class: PPEACT - Messages for iPPE ACT Application (Activities)
Message number: 456
Message text: Component &1 &2 is not assigned to activity &3
No valid connection between the activity and component could be
determined, as a component for an activity was assigned to a production
supply area.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Select only components and variants for PVB assignment, which are also
directly assigned to the current activity.
Error message extract from SAP system. Copyright SAP SE.
PPEACT456
- Component &1 &2 is not assigned to activity &3 ?The SAP error message PPEACT456 indicates that a specific component (identified by &1 and &2) is not assigned to the activity (identified by &3) in the context of production planning or project management. This error typically arises in scenarios involving production orders, project systems, or when working with activity-based costing.
Cause:
- Missing Assignment: The component has not been assigned to the specified activity in the system.
- Incorrect Configuration: The configuration settings for the activity or component may not be set up correctly.
- Data Inconsistency: There may be inconsistencies in the master data or transactional data related to the components or activities.
- Authorization Issues: The user may not have the necessary permissions to view or modify the assignments.
Solution:
Check Assignments:
- Navigate to the relevant transaction (e.g., CO02 for production orders, CJ20N for project management) and verify if the component is correctly assigned to the activity.
- If not, you will need to assign the component to the activity.
Update Master Data:
- Ensure that the master data for the component and activity is correctly maintained. This includes checking the Bill of Materials (BOM) and routing for production orders or the Work Breakdown Structure (WBS) for project activities.
Review Configuration:
- Check the configuration settings in the SAP system to ensure that the component and activity are set up correctly. This may involve consulting with your SAP configuration team.
Authorization Check:
- Verify that the user has the necessary authorizations to access and modify the relevant data. If not, contact your SAP security team to request the appropriate permissions.
Consult Documentation:
- Refer to SAP documentation or help files for specific guidance on the error message and related processes.
Testing:
- After making the necessary changes, test the process again to ensure that the error does not reoccur.
Related Information:
By following these steps, you should be able to resolve the PPEACT456 error and ensure that the component is properly assigned to the activity in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
PPEACT455
Object &1 &2 &3 &4 must be completely described
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEACT454
Component &1 &2 &3 &4 must be completely described
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEACT457
Component &2 cannot be assigned to setup activity &1
What causes this issue? You have tried to assign a component from the product structure to a setup activity. This assignment is not allowed.System Re...
PPEACT458
Only 'start' or 'no' consumption allowed in the &1 from &2 to &3
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.