Do you have any question about this error?
Message type: E = Error
Message class: /PM0/ALP_BTX -
Message number: 095
Message text: Payout date &1 must be earlier than contract end &2
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/PM0/ALP_BTX095
- Payout date &1 must be earlier than contract end &2 ?The SAP error message
/PM0/ALP_BTX095 Payout date &1 must be earlier than contract end &2
indicates that there is a validation issue with the payout date in relation to the contract end date in the system. This error typically arises in the context of contract management or financial transactions where a payout is being processed.Cause:
The error occurs when the payout date specified in the transaction is set to a date that is equal to or later than the contract end date. This is a logical validation to ensure that payouts are processed within the valid timeframe of the contract.
Solution:
To resolve this error, you should take the following steps:
Check the Payout Date: Review the payout date you have entered. Ensure that it is set to a date that is earlier than the contract end date.
Verify Contract End Date: Check the contract end date associated with the contract in question. Make sure you understand the terms of the contract and the valid payout period.
Adjust Dates: If the payout date is incorrect, adjust it to a date that is earlier than the contract end date. If the contract end date is incorrect, you may need to update the contract details, but be cautious as this may have implications on other transactions.
Consult Documentation: If you are unsure about the correct dates or the implications of changing them, consult the relevant SAP documentation or your organization's policies regarding contract management and payouts.
Test the Changes: After making the necessary adjustments, attempt to process the payout again to ensure that the error is resolved.
Related Information:
VA01
, VA02
, etc.).By following these steps, you should be able to resolve the error and proceed with the payout process.
Get instant SAP help. Start your 7-day free trial now.
/PM0/ALP_BTX094
Only possible to create payment after reconfiguration of contract
What causes this issue? You need to create a one-time payment for a <DS:GLOS.1B7CD050E4F95444B757903A76D37757>benefit part</> before the ...
/PM0/ALP_BTX093
Premium exemption date &1 must be earlier than contract end &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
/PM0/ALP_BTX096
Premium exemption date &1 must be later than contract status date &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
/PM0/ALP_BTX097
Adjustment start must be one year after contract start (at the earliest)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.