Do you have any question about this error?
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 590
Message text: Relationship & is to an activity which does not exist
The MPX file contains relationships to an activity that does not exist.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
RESET N1
Correct the relationship in the MPX file.
Call up the MPX file in Microsoft Project (R) and correct the
relationship. Recreate the MPX file.
Error message extract from SAP system. Copyright SAP SE.
PJ590
- Relationship & is to an activity which does not exist ?The SAP error message PJ590, which states "Relationship & is to an activity which does not exist," typically occurs in the context of project management within SAP, particularly when dealing with project structures and relationships between activities in a project.
Cause:
This error usually arises due to one of the following reasons:
Invalid Activity ID: The activity ID referenced in the relationship does not exist in the project. This could happen if the activity was deleted or if there was a typo in the ID.
Incorrect Project Structure: The project structure may not be correctly defined, leading to references to activities that are not part of the current project.
Data Consistency Issues: There may be inconsistencies in the project data, possibly due to incomplete data entry or issues during data migration.
Authorization Issues: Sometimes, the user may not have the necessary authorizations to view or access certain activities, leading to the perception that they do not exist.
Solution:
To resolve the PJ590 error, you can take the following steps:
Verify Activity ID: Check the activity ID mentioned in the error message. Ensure that it is correctly spelled and exists in the project. You can do this by navigating to the project structure and confirming the activity's presence.
Check Project Structure: Review the overall project structure to ensure that all activities are correctly defined and that there are no missing links or relationships.
Recreate the Activity: If the activity has been deleted, you may need to recreate it and then re-establish the relationships.
Data Consistency Check: Run consistency checks in the project to identify any discrepancies. This can often be done through transaction codes like CJ20N (Project Builder) or CJ02 (Change Project).
Authorization Check: Ensure that you have the necessary authorizations to view and modify the activities in the project. If not, contact your SAP administrator to grant the required permissions.
Consult Documentation: Refer to SAP documentation or help resources for additional guidance on managing project structures and relationships.
Related Information:
By following these steps, you should be able to identify the root cause of the PJ590 error and implement a suitable solution.
Get instant SAP help. Start your 7-day free trial now.
PJ580
Error in relationship: & (Please correct)
What causes this issue? The MPX file contains an erroneous relationship.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX...
PJ570
Unit & not allowed here (only particular time units allowed)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PJ600
Relationship & to group of activities is not supported
What causes this issue? You have maintained relationships to collective activities in Microsoft Project (R). The project system does not recognize co...
PJ610
Relationship & between different alternatives not permitted
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.